For the record: Feasibility study for Penang undersea tunnel project completed

27.9.2021: Feasibility study for Penang undersea tunnel project completed, says Chow (See Project Cost below).

SOURCE: Bernama via The EdgeMarkets – September 27, 2021 15:19pm

GEORGE TOWN (Sept 27): The feasibility study for the undersea tunnel project has been completed and will be presented to the state executive council meeting after receiving feedback from the relevant federal and state technical agencies.

Chief Minister Chow Kon Yeow, in a statement on Monday, said the undersea tunnel project was part of the three major roads and undersea tunnel projects in Penang.

He said the cost for the feasibility study and detailed design of the four packages (three highways and an undersea tunnel) was RM305 million.

“However, only RM208 million has been paid through the land exchange method to the Zenith Construction Consortium (CZC) contractor for the feasibility study and detailed design of the three highways only.

“No payment has been made for the undersea tunnel because the feasibility study has not been received and approved by the state government,” he said.

On the proposal to replace the undersea tunnel with a bridge, Chow said the feasibility study conducted by CZC was for an undersea tunnel only and not for the construction of a bridge.

However, he did not rule out the possibility of building a bridge as a third link, adding that any decision on the matter would only be made after the feasibility study was officially presented to the state government.

Reference URL: https://www.theedgemarkets.com/article/feasibility-study-penang-undersea-tunnel-project-completed-says-chow

1 Trackback / Pingback

  1. News-clip: Undersea tunnel or 3rd bridge both not viable for now: ex-Consortium Zenith staff – jeffooi.com